Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In Primavera P6, Why assigned Baseline is unable to export with Updated Program?

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/07/11
ABDULLAH SALAH
by ABDULLAH SALAH , Planning and Control Manager , Haddadin Engineering Co. For Contracting

Assigned Baselines could't be imported/ exported within the schedule in P6 Professional, you should import a separate copy of the Baseline.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.