Decisions as to the types of projects that should be accomplished and strategic plans as to the quality of the projects that are required should be the decision of which of the following?

 are required should be the decision of which of the following?

a. Project manager b. Procurement manager c. Upper management d. Stakeholders

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/27
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Suresh Kumar option C is correct

Sathish Prabhu.V
by Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Upper management decides the Project and the strategic plans

sardar mardookhy
by sardar mardookhy , PMP certified Project manager , MCCI

Option C.........

Thanks.......................

Option C  seems to be the appropriate answer.

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

..............c. Upper management...........

Usman Islam
by Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

option A in my opinion would be the correct asnwer

Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

I think the answer is:

c. Upper management