Project Cost Management includes all of the following processes except: A- Estimate Costs. B- Level Resource. C- Determine Budget. D- Control Costs?

user-image
Question added by KHALED ALABOUDI , US TAX ADVISORY , US TAX GLOBAL SERVICE LLC
Date Posted: 2016/05/20
Nadjib RABAHI
by Nadjib RABAHI , Freelancer , My own account

Except :

B : Level Resource

Asif Niaz
by Asif Niaz , Senior Quantity Surveyor , The Associated Engineering Partnership

Its B "Level Resource", Project Cost Management is a series of activities for estimating, allocating, and controlling costs within the project. It allows determining and approving budget for the project and controlling spending.