a. Actual cost
b. Estimate at completion
c. Earned value
d. Budget at completion
Agree with all experts answer <<<<<<<<<<<<,,,
thanks for invition ,,,,,,,,,, my choice is option C
earned value is the right answer
C is my answer.................
C. Earned Value...............Earned Value is the value of the work actually completed to date,