What is 'Load Capacity Analysis' term used by Planning Engineers?

user-image
Question added by Shahed Ali Mir , Project Engineer , Saudi Electricity Company
Date Posted: 2016/04/21
Nitin Choudhary
by Nitin Choudhary , Assistant Manager - Planning & Inventory Management , Green Planet Industries

This analysis is a basic of "Capacity Planning"

 

- Load is the possible work load planned in the near future. (Derived in hours using the standard routing)- Capacity is the available work hours after considering OEE.(If it a combination of work centers, consider the minimum as the available hours)

 

The load and capacity analysis is generally used to determine if the capacity would meet the near future demand or not.