What is the minimum size of transformer room that should be protected by CO2 fire protection system?

user-image
Question added by Abdelrahman Mohammed , Project Engineer , Heatco International for Steam and Hot Water Boilers
Date Posted: 2016/04/18
Faizur Rehman
by Faizur Rehman , MEP Manager , REDCO INTERNATIONAL

Wherever a firewall is installed between transformers, it should extend at least 1 ft (0.31 m) above the top of the transformer shell and oil tank and at least 2 ft (0.61 m) beyond the width of the transformer and cooling radiators.