How can you claim extension of time for activities / packages that are not on the critical path, I mean is it really doable?

user-image
Question added by mohamed mansour , Planning and Controls Lead Engineer (act as: Project Controls Manager) , Arabian Bemco Contracting co. ltd.
Date Posted: 2013/05/01
Binil Paul
by Binil Paul , Senior Planning Engineer , Keo International Consultants - Qatar

sometimes when you insert the delay activity in the non critical activity, it changes the crtitical path and the crtitical path might vary. So it can also be used for EoT

islam zkrallah
by islam zkrallah , رئيس قسم المطالبة القضائية - باحث تنمية أدارية , مجمع محاكم مجلس الدوله

Motivational plans for workers increase their loyalty and affiliation to the company, after achieving the goal motivating rewards

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.