What is the production rate of MEP works/activities specifically Electrical works for villas and high rise buildings w.r.t man power. And what is the difference if precasted walls are used instead of block works?

user-image
Question added by Muhammad atif khan , Project Manager , Sunnel Middle East Solar Energy systems Contracting LLC
Date Posted: 2016/02/25
hasnianwazir muhammad wazir
by hasnianwazir muhammad wazir , apprentice condidate , public organization

dear

 for villas you need maximum 35 labours( 20+electrician +7 HVAC technician +6plumber)to comlete one villa in 20 days.maximum time to complete one villa is 7000 man hours.

               for high bulding you will need above labours,technicain,plumber/electricain but for single flour you will just spend 5200 man hours.

  regards

     hasnain

Bassel Laz
by Bassel Laz , MEP Project Manager , Saudi Amana Contracting

Dear Mohammad,

 

For villas, you roughly need 35 labors (20 Electrician + 8 HVAC Technician + 7 Plumbers) to finish one villa in 20 days - Approx you will spend 7000 man.hours on one villa.

 

For high rise buildings, you will need the above labors but to finish one floor in 15 days. So you will spend 5250 man.hours.

 

For Precast walls and slabs, they are usually easier to construct and much faster to install. They are amazing structures that can save enormous time in your schedule since these structures are cast at the concrete plant and then brought by a tower crane to the exact location. The problem in using precast is once you provide your embedded MEP services it is difficult to rectify and change them since this is concrete we are talking to about.

 

Hope this can give some information. If you need further work rates for MEP please don't hesitate to contact me at

 

Regards,

 

Basel

BLAISE  TANWIE
by BLAISE TANWIE , Agile Delivery Lead , DP World

For  villas you need maximum 35worker ( 20 electricians, +7 H VAC Technicians and +8 plumbers) to complete the villa in maximum 20 days. You will spend  700 days work man hours. While for precast walls and slabs once it would not be easy to correct a problem since the pipes and cables are already embedded.

juby jose
by juby jose , Junior Electrical Engineering , Believer's Hospital

For villas you need maximum 30 labours(13 electricians+9 H vac tecnicians +8 Plumbers ) to complete one villa in 18 days.Maximum days to work is 6000 Man Hours.