How to plot an S-curve in excel based on the schedule created in Primavera?

user-image
Question added by PRAJEESH PRASAD , planning engineer , Technical Engineering Service
Date Posted: 2016/01/11
Ali Zeeshan Anwar
by Ali Zeeshan Anwar , Planning Engineer , sinotec

Hi Prasad,

if i understand correctly , you want to use information from primavera to be presented in excel. for this you take individual values of actual  and planned percentages for different months  , use them to find cumulative percentages and put these values in the graph table in excel .hope this help