What is loop testing during commissioning of a plant and how it is done?

user-image
Question added by MUHAMMAD ANJUM , PRODUCTION SUPERVISOR , DAMMAM
Date Posted: 2015/12/15
MUHAMMAD SHAHID MEHMOOD ARAIAN
by MUHAMMAD SHAHID MEHMOOD ARAIAN , Electrical Senior Technician , GDFSUEZ, HUBPOWER PLANT

LOOP TESTING IS BASICALLY WIRING HEALTH CHECK AND VERIFICATION OF TAGG IN CONTROL ROOM, 

 

WE INITIATE AND ALARM , OR TRIP, BY OPENING WIRE OR CLOSING CONTACT BY JUMPER FALSE AND THEN CHECK OPERATES THE LOGIC AND SHOW ALARM IN CONTROL ROOM AND RECORD ON EVENT AND CREATE TRIP , SO IT IS CONFIRMED THE OUR LOOP IS OK, AND NAME OF APPEARING ALARM OR TRIP IS CORRECT, 