Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How to install Piggyback CP System for fixed roof tank for a diameter of 200 ft. with 19 columns inside?

As this system should be concentric / circular loop

user-image
Question added by Raghavendra kumar Bondada , Mechanical Engineer , KNPC
Date Posted: 2015/11/23
Bright Matesanwa
by Bright Matesanwa , Boilermaker , GHH Mine Machines

fabricate the flow plate on site then the shell put main hole. mark position of the columns starting from the center going concentric equally spaced then at last put the conical or doomed roof.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.