The stage of completion of a construction contract may be determined by:

a. Comparing the costs incurred for the work performed to date with the estimated total costs b. Carrying out a survey of the work performed to date c. Considering the physical proportion of the contract work completed d. Any of the above

user-image
Question added by Deleted user
Date Posted: 2013/08/28
Anisuddin Siddiqui
by Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture

d

Tarek Ghanem
by Tarek Ghanem , Building package manager , Safari Group

a plus b plus c plus review the payment certification from the owner which collect all data till final one.