Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Cost performance measurement is BEST done through which of the following?

A. Asking for a percent complete from each team member and reporting that in the monthly progress report

B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance

 

C. Using the50/50 rule and making sure the life cyde cost is less than the project cost

 

D. Focusing on the amount expended last month and what will be expended the following month

user-image
Question added by Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants
Date Posted: 2015/08/03
Aahyan Mumtaz
by Aahyan Mumtaz , Investment Associate - Growth Equity , Cyan Limited

Option B - Comparing earned value to a measure of input prices (as captured by indexes)

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.