During which stage of risk planning are risks prioritized based on probability and impact?

 

a) Perform Qualitative Risk Analysis

b) Monitor and Control Risks

c) Plan Risk Management

d) Identify Risks

user-image
Question added by Nancy Refai , Health, safety and environmental management Trainer and consultant , Freelancer
Date Posted: 2015/04/28
Javed Khan
by Javed Khan , Deputy General Manager Marketing and Sales , InSolare Energy Pvt Ltd

it should be Perform Qualitative Risk Analysis as in this stage only we prioritized risk as High and Low based on there probability and impact.

Firstday Jesse
by Firstday Jesse , Sales Representatives , Nigerian Bottling Company Limited Lagos

d) %%%%********0()Identify Risk%%%%%%^#$##%%^&$$

Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

^^^^^^^^^^^^^^^^^^^^a) Perform Qualitative Risk Analysis^^^^^^^^^^^^^^

PURUSHOTHAM Chandra
by PURUSHOTHAM Chandra , Senior Financial Analyst , Dell EMC

My Answer is 

>>>>(a) Perform Qualitative Risk Analysis

I will go with A.

Qualitative analysis and(or) quantitative analysis is the stage that will help in prioritize risk or in other words in ranking risks.

Shaik Mahaboob Subhani
by Shaik Mahaboob Subhani , Strategy IT Head , Annapurna Finance

Risk is always Risk :)

 

Risk Analysis means you are in the Project Planning Stage not in Execution.  Probability/Impact is part of   Qualitative Risk Analysis.

 

Mohamed El Sayed
by Mohamed El Sayed , Senior project manager , Solid Constriction S.A.E.

as an output from perform qualitative risk analysis project document update which include update risk register and prioritize the the risk based on its probability and impact  

Nancy Refai
by Nancy Refai , Health, safety and environmental management Trainer and consultant , Freelancer

a) Perform Qualitative Risk Analysis

NISHA SUKESH
by NISHA SUKESH , Manager , K Raheja Corp

Qualitative Risk Analysis.

Khaled Anwar
by Khaled Anwar , Senior Sales Engineer , "Automotive company''

I think the answer is:  ( a ) Perform Qualitative Risk Analysis

Emad Mohammed said abdalla
by Emad Mohammed said abdalla , ERP & IT Software, operation general manager . , AL DOHA Company

>>>>>>>>>>> a) Perform Qualitative Risk Analysis >>>>>>>>>>>>