Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

A test and balance report has been submitted without documentation of domestic hot water recirculation readings.

What action should the CA take to address this omission?

A. Reject the report for being incomplete. 

B. Review the specification to determine if domestic water systems are included in the test and balance 

scope. 

C. Return the report to the contractor with a request to complete the domestic hot water recirculation

balance. 

D. Request that the mechanical contractor submit a test report for the domestic hot water recirculation 

system.

user-image
Question added by LABIB KOOLI , Director of the Sectoral Center for Training in Hotel Technologies at Southern Hammamet , Tunisian Vocational Training Agency (ATFP)
Date Posted: 2015/04/05
Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

B. >>>>>>>>>>>>>>>> Review the specification to determine if domestic water systems are included in the test and balance scope. 

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

First B (something to do in front!) and then depending on the type of contract for the Project ask for C or D.

hatem labib
by hatem labib , Quality control manager , MISER consultant

start with action B and all other choice A, C , D can use after

Thanks for the invitation 

  B. 

Is suitable 

 

I would choose option (B) Review the specification to determine if domestic water systems are included in the test and balance scope. 

syed tahmul ullah hussaini
by syed tahmul ullah hussaini , SENIOR MECHANICAL ENGINEER , SAUDI BINLADIN GROUP

REVIEW THE SCOPE OF CONTRACTOR  SO B IS THE APPROPRIATE CHOICE .REST OF THE DECISIONS CAN BE TAKEN AFTER THIS CONFIRMATION.

Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

When we turned in test reports and something been missing the report came back as rejected due to missing information and we had to complete the test or furnish the missing parts... therefore I would go with answer 

C. Return the report to the contractor with a request to complete the domestic hot water re-circulation balance. 

 

I paid for a service and want it done right and not doing parts of the contractors work or hire an other to finish the job.

I only do it when I have no time and need it ASAP, but than give the vendor a payment penalty for incomplete work...

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.