What is Back Scheduling in MRP?

Select one:a. Production scheduling for the previous periodb. Analyzing the Lead times of materials and working backwards to raise the PO earlier to ensure timely delivery of materialsc. Taking back up of Scheduling Datad. All the above

user-image
Question added by Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG
Date Posted: 2015/03/01
Wasi Rahman Sheikh
by Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Answer is option b.Analyzing the Lead times of materials and working backwards to raise the PO earlier to ensure timely delivery of materials