Which option use for Under Reamed Piles? A. Machine foundation B. Factory buildup C. Transmission line tower D. Tall structure E. All of them

user-image
Question added by Muhammad Shakeel , CAD Design Manager , M/S zeeruk Intl.
Date Posted: 2015/01/15
Basit Ali
by Basit Ali , Director of Engineering , Laverda Suites & Villas / Blue Bay Resorts

E is right option 

Mahmoud Zaher Tarakji
by Mahmoud Zaher Tarakji , مدير , أوال جاليري

E. all of them , so for me better ( c 

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

E. All of them

Muhammad samran
by Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

The option is E. All of them.

RAJ DAHIYA
by RAJ DAHIYA , Senior MEP Projects Manager , Trinity Engineering Services L.L.C.

Endorse answer from Experts !!

Muhammad Shakeel
by Muhammad Shakeel , CAD Design Manager , M/S zeeruk Intl.

Thanks for Your Great Contribution.    ...........    Good day

E. All of Them is Correct Answer.

Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

I go with Option E;

It looks to me is this form of stabilization or rather to secure foundations for machines, buildups for factories, tall structures, and more.... 