You are working on the project of painting of your house. You identify a dependency that the painting of roof should begin only

<p> after two days of completion of painting of walls. This is an example of</p> <p>a.Lag b.Lead c.Slack d.Float</p>

user-image
Question added by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date Posted: 2015/01/07

Hi...

This is an example of lag...

kevil Vavaiya
by kevil Vavaiya , Civil Engineer , ASCO Consulting Engineers

Answer is A) Lag

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

A: Lag is the amount of time after the completion of the predecessor activity, when the successor activity can start.

mohamed shaaban ramadan moursi moursi
by mohamed shaaban ramadan moursi moursi , project manager , PEAKS CONSTRACUTIONS & MAINTANANCE COMPANY

a.) Lag

Dejan Petrovic
by Dejan Petrovic , Director , virtualarchitecture d.o.o.

a. Lag

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The correct answer is

a. Lag

Elias Gaouro
by Elias Gaouro , Sr. Procurement Engineer , INCO INTERNATIONAL FZC

A

Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

my choice is a) Lag