Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What are the major differences between turn-key project and contract by valuation?

user-image
Question added by Mayowa Olayiwola Abdul , Project Manager , BETON BAU NIG LTD
Date Posted: 2014/12/17

1- Turnkey system that would be appropriate in the case of small projects while large and complex projects require more specialized destinations where it is better integrated contracts 

 

2- In turnkey projects we use (union  total Pricing system) "stint price ." And there is no pricing for business items  while contract projects evaluated by giving price to each item as well as duration of performance 

جعفر هندي زين السقاف
by جعفر هندي زين السقاف , مهندس أستشاري , مشاريع اﻻشغال العامة

Turn-key project where the contractor or provider undertakes the entire responsibility from design through completion and commissioning. The client or customer only has to turn the proverbial key to make everything function as it should, where contract by valuation is "Final negotiated or proposed price of a contract".

Mubarak Salahudeen
by Mubarak Salahudeen , Senior Civil/Structural Engineer , Shell Petroleum Development Company

Dear Ola,

This is Salahudeen, please get in touch. My e-mail is .

Regards,

Salahudeen

 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.