Based on draft project BRD, how to estimate the required time needed to collect the full project requirements?

When your project manager handle you a contract, Agreement, draft BRD, or any sign off document, he will ask you "How long do you need to complete the stage of Requirements Gathering ?" here what theoretically is the best method/s to estimate this?

user-image
Question added by Issa Salameh , Business Analyst , Fujitsu
Date Posted: 2014/08/17
Hesham Abou Hussein
by Hesham Abou Hussein , General Manager , Agricultural Bank of Egypt

Clearly specify all LOB's involved in the required draft.

Identify the required tasks for each involved LOB.

Identify the estimated time for achieving every task.

Identify the estimated time for CBS readiness.

Identify the estimated time for regulating procedures sign off.

Complete the BRD document ready for sign off by all involved LOB. 

Amol Gawde
by Amol Gawde , Business Systems Analyst , Mphasis UK Ltd

Tips for Estimating Requirements:

  • Break the effort into manageable pieces.
  • Choose your approach.
  • Use a variety of estimating techniques.
  • Brainstorm.
  • Identify all the deliverables/artifacts.

Rekha Dighe
by Rekha Dighe , Digital Project Manager , Indigo Consulting and Technology Systems

Depends on the project. A project manager who had handled many projects can easily estimate the time required if the project requirements are fairly the same as his/her previous projects. On the other hand if the project requirements are new and unclear it might take more time to estimate.

Nilima Rout
by Nilima Rout , Digital Analyst/Product Owner , Al Futtaim Group

Estimation depends on the type of project you are doing. If something that is already been established and you are adding new features, estimation can be done based on the experience of developing similar features. Well defined business use case will accelerate the process. 

But if the project use cases are fairly new and ambiguous, then estimating the time to develop the requirement is all about guessing game. From your past experience you can estimate how much time it will take to develop the requirements and give a rough estimate. It is better to interview the stakeholders to hash out the use cases and requirements in case of ambiguity.  

Timeline includes below method1. Initiate Project plan2. Research & Findings3. Approval from stake holder to fulfill customer needs4. Pilot project initiation5. Final Verdict