Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is the different between the common order lists of materials against lead time order lists of materials?

The question above is very important to all PM who are handling projects either you are Contractor or Project Management or Client Representative who do Owner Supply for the projects. So we request you to explore!

user-image
Question added by Rolly Custodio , Civil and Structural Engineer , Jacobs Zate Consulting Engineers
Date Posted: 2014/07/13
Ga GI
by Ga GI

Common order list of materials can be ordered just in time when required due to their stock availability but Lead time order list have to considered critical as it needs planning within the lead time to get the materials available on time to meet the demands.