ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Is Start to finish relationship ever used in scheduling? Can you provide me with examples?

user-image
تم إضافة السؤال من قبل Ghada Sameer , Project Manager and media executive , CQA
تاريخ النشر: 2014/05/28
Mohammed Thiab
من قبل Mohammed Thiab , Founder / Chief Consultant , MV Consulting

Start-to-finish occurs when “the completion of the successor activity depends on the initiation of the predecessor activity,” or, said so that normal folks can process it: Activity A must start before Activity B can finish.

 

The most common examples are those associated with replacement of an old system by a new one as in the case of upgrades, replacements, obsolencence, ...  etc

 

In these case ...  activity A (the retirement of the old system) can NOT start until activity B (preparation of the new system to replace the old one) has already been finished !!

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟