Being the project manager in a high risk electronics project with a lot of new technologies, you developed a Risk management plan ?

and identified risks which you documented in a Risk register. Then, the risks were analyzed and response planned. It is getting obvious during Risk monitoring and control meetings: The documents which you created are not very helpful. What have you probably done wrong? A. You did the first processes alone. B. You did not identify Triggers. C. You failed to use an RBS. D. You did not calculate EMVs.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/10/03
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. You did the first processes alone.