ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Dave is the project manager for a construction project that is building a gazebo. When the project first started, he met with the stakeholders ?

to define the scope. The sponsors mentioned that the gazebo is a really important part of their daughter's wedding ceremony that was planned for7 months from then. In fact, they said that if the gazebo couldn't be completed in7 months, it wouldn't be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section of the document did the deadline appear? A. Project Deliverables B. Project Objectives C. Project Constraints D. Project Assumptions

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/09/05

Thanks for invite Mr.Farook -

I agree with your answer - Important explanation   !!!

 

Regards * 

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: Since the project absolutely must be completed in 7 months for it to be worth doing, the deadline is a constraint. It must be met for the project to be considered successful.

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟