You are managing a project with a total budget of $450,000. According to the schedule, your team should have completed 45% of the work by now.?

But at the latest status meeting, the team only reported that% of the work has actually been completed. The team has spent $, so far on the project. How would you BEST describe this project? A. The project is ahead of schedule and over its budget B. The project is behind schedule and within its budget C. The project is ahead of schedule and within its budget D. The project is behind schedule and over its budget

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/08/29
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: If you want to evaluate how the project is doing with respect to the schedule and budget, you need to calculate CPI and SPI. The first step is to write down the information you have so far: BAC = $450,000, planned % complete = 45%, actual % complete = 40% and AC = $165,000. Now you can calculate PV = BAC x planned % complete = $450,000 x 45% = $202,500. And you can calculate EV = BAC x actual % complete = $450,000 x 40% = $180,000. Now you have the information you need to calculate CPI and SPI. CPI = EV / AC = $180,000 / $165,000 = 1.09, which is above 1.0 - so your project is within its budget. And you can calculate SPI = EV / PV = $180,000 / $202,500 = .89, which is below 1.0 - so your project is behind schedule.

Muhammad Nadeem
من قبل Muhammad Nadeem , Manager Administration , China state Construction Engineering Corporation

B the Project is behind schedue and within its budget.

 

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with the answer Mohammed Farouk

With greetings and appreciation

Thanks Mrs.Lana for invite ;

Fully agree with Mr.M.Farook answer [complete details] !!!

 

Regards .

sabah lamamra
من قبل sabah lamamra

A. The project is ahead of schedule and over its budget

Eric Celestino
من قبل Eric Celestino , electrical technician , Gedac Electric

must write and good detail how many percent cost of the project

Tuyizere Gideon
من قبل Tuyizere Gideon , general cashier , Lemigo hotel

yes, I might do the task according to the discussion