ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Brandi is a project manager on a software project. About halfway through development, her team found that they had not estimated ?

enough time for some of the technical work they needed to do. She requested that the new work be added to the scope statement and that the time to do the work be added to the schedule. The change control board approved her change. What's her next step? A. Update the scope and schedule baselines to react the approved change. B. Gather performance metrics on the team's work so far. C. Start doing the work D. Perform Quality Assurance

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/06/06
Niranjan Bokil
من قبل Niranjan Bokil , Head-Operations , Signode India Ltd

Brandi needs to update the scope and scheudle baseline.

Rahul Nutalapati
من قبل Rahul Nutalapati , Freelance Photographer , Infinite stories

A. Update the scope and schedule baselines to react the approved change.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: When a change has been approved you always need to update the baseline and then implement the change. That way, you will be sure to track your performance versus new scope and schedule expectations and not the old ones.

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟