ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are the project manager for a construction company that is building a new city and county office building in your city. Your CCB recently?

approved a scope change. You know that scope change might come about as a result of all of the following except which one?

A. Product scope change

B. Changes to the project requirements

C. Schedule revisions

D. Changes to the agreed-upon WBS

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/08/26
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

Scope changes will cause schedule revisions, but schedule revisions do not change the project scope. Project requirements are part of the project scope statement, and therefore D is one of the correct responses.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟