You've just completed the WBS. Which of the following statements is true?

A. The WBS breaks the project deliverables down to a level where alternatives identification can be used to determine how level-two assignments should be made.

B. The WBS breaks the project deliverables down to the work package level, where product analysis can be documented.

C. The WBS breaks the project deliverables down to the work package level, where cost and time estimates can be easily determined.

D. The WBS breaks the project deliverables down to a level where project constraints and assumptions can be easily identified.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/06/12
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

B. The WBS breaks the project deliverables down to the work package level, where product analysis can be documented.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. The WBS breaks the project deliverables down to the work package level, where cost and time estimates can be easily determined.

Explanation: The work package level is the lowest level in the work breakdown structure. Schedule and cost estimates are easily determined at this level.