ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

If the Earned Value is equal to Actual Cost, What does it means?

A. Project is on budget and on schedule

B. There is no schedule variance

C. Schedule Variance Index is1

D. There is no cost variance

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/05/05
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The correct answer is A.

A. Project is on budget and on schedule

ZULFIQAR ALI
من قبل ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

If there is no difference between earned value and actual cost it means that proejct is on budget and schedule.

My answer is A

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is A

Keith Gregory Wright
من قبل Keith Gregory Wright , Program Director , DynCorp International

Your project is in trouble. A successful project needs sufficient income to cover direct and indirect costs as well as profit, i would hope that my projects earned value is greater than actual cost, if not i would need to have a strategy to recover losses eg variations etc. Measuring financial position is always problematic as resource costs are realised on different cycles, and as such there are difficult to asses because of the delays. 

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the correct choice

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you option A is good answer.

Krishna Avtar Choudhary
من قبل Krishna Avtar Choudhary , Security Officer , Spicejet Limited

If is an business in a initial stage then its good, and called the no loss no profit stage or break even point. So A

Nagoor Khan
من قبل Nagoor Khan , Transport Manager , worked with different Organizations mentioned in my Resume

The Actual Cost (AC) is a function of the time and it is a measurement of how much money has been spent on a project. It's measured in units of economic value ($). Mathematically, the domain of the Actual Cost (AC) is time and the range is an economic value ($). The Actual Cost (AC) is clearly associated with the Earned Value (EV) because the units of work that are measured by AC, are the same that EV has added as progress. In other words, when a unit of work has been done, EV adds the planned value of cost for that unit of work and AC adds the real cost for that unit of work.

Faheem Memon
من قبل Faheem Memon , Resident Engineer / Discipline Lead , WSP

I have the same situation, but still my SV is negative and SPI is below 0.. How come?

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟