ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The Critical Path Method of scheduling is?

 

A. A technique that uses sequential network logic for schedule development

B. A mathematical analysis technique for Develop Schedule

C. A technique that uses weighted averages to calculate project duration

D. A technique that allows for probabilistic treatment of both network logic and activity duration

estimates

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/04/28
Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with option A & thanks for the invite.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion

A. A technique that uses sequential network logic for schedule development

D. A technique that allows for probabilistic treatment of both network logic and activity duration estimates

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟