ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Your project is progressing as planned. The project team has come up with a demo that the sales team will use when making presentations?

to prospective clients. You will do which of the following at your next stakeholder project status meeting?

A. Report on the progress of the demo, and note that it's a completed task.

B. Preview the demo for stakeholders, and obtain their approval and sign-off.

C. Review the technical documentation of the demo, and obtain approval and sign-off.

D. Report that the demo has been noted as a completed task in the information retrieval system.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/04/20
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

B. is the correct answer. Preview the demo

 

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion

A. Report on the progress of the demo, and note that it's a completed task

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I prefer to with option - B and thanks for the invite.

Sattar Abdulkarim  Mohamed
من قبل Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

My answer is Option B which is more convenient to get approval and satisfaction of the stakeholders.

B. Preview the demo for stakeholders, and obtain their approval and sign-off.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟