ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called?

 

A. Trend analysis

B. Earned value reporting

C. Variance reports

D. S curves

E. Baseline control

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/02/11
MAJED AL-HARBI
من قبل MAJED AL-HARBI , Network and Computer Specialist , Rent Human Resources

The answer is: D. S Curves

a ccumulated data a gainst time called  S Curves

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. S curves  --------------------

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is 

Md Fazlur Rahman
من قبل Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

A. Trend analysis.................................

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟