ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization's operating system on 236 servers? You performed this project under contract. You are in the Closing process and know that product verification is for what purpose?

A. To verify that all the work was completed correctly and satisfactorily

B. To evaluate project goals and ensure that the product of the project meets the requirements

C. To verify the goals of the project and ensure that the product of the project is complete

D. To evaluate all the work of the project and compare the results to project scope

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/02/03
Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is option A

mujahid khan jutt larr
من قبل mujahid khan jutt larr , computer work , progressive college

Thank u for inviting to verify the goals of the project and ensure that product of the project is complete My answer is option (c)

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. My answer is Option A. To verify that all the work was completed correctly and satisfactorily.

Hatem Labib
من قبل Hatem Labib , Q/C manager , SOGREAH consultant office

Option A

thank you for invitation

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

I think option A  ---  To verify that all the work was completed correctly and satisfactorily

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

 I agree with  answer C

Ashraf ELBasyouni
من قبل Ashraf ELBasyouni , PMO DIRECTOR , Hydro for Environmental and Infrastructure Studies

 

  • B. To evaluate project goals and ensure that the product of the project meets the requirements

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with option B - Confirming work is done to the requirements and gaining final acceptance of the product is an important activity of closing process .

Sattar Abdulkarim  Mohamed
من قبل Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Appreciation for your invitation. It is Option C - To verify the goals of the project and ensure that product of the project is complete. 

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟