In order to produce a cost base line,the project manager requires?

 

 

A. Work packages,work breakdown structure and project schedule

B. cost estimates,work breakdown structure and the project schedule.

C. cost estimates, work packages `and project schedule.

D. cost estimates ,work packages and work breakdown structure.

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/11/26
Javad Taghavi
من قبل Javad Taghavi , Program Manager, Senior Adviser in Project Management , KCE Co.

The processes for cost baseline are:

- estimate activity cost: 

decomposing of work packages to activities and estimating cost for each activity by applying appropriate tools and techniques.

- determine budget:

Rolling up and aggregating activities cost with considering contingency reserve and finally checking cash in with cash out if cash out is bigger than cash out, usually we have to change project schedule to reduce the cash out.

Then we need to work packages, activities cost estimate and project schedule 

So, the option C should be correct 

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

IN MY OPINION OPTION B IS MORE CLOSED TO QUESTION

vikrant k Jaitly
من قبل vikrant k Jaitly , Chief of Operations , Ministry of Defence

C is the correct answer since cost base line only looks at cost estimates what all work packages that will be involved and how long the project schedule will be.