ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What are the steps you should take formally to stop the project?

A. generating ,gathering and disseminating information to formalize the phase or project complition.

B. collecting and disseminating performance information.

C. completing and settling conracts, including resolution of any open items.

D. both A and C

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/09/30
Nadjib RABAHI
من قبل Nadjib RABAHI , Freelancer , My own account

The answer is : Option D- both A and C

The steps :

1- Knowing the reasons  .... (+ yes or - no )

2 - Study contracts ..... (+ yes or - no )

3- Comparison of actual and theoretical costs .... (+ yes or - no )

4- Follow-up workers and working ..... (+ yes or - no )

5- Review project materials ..... (+ yes or - no )

6- Review schedules ..... (+ yes or - no )

7- Audit of the financial and moral benefits ...... (+ yes or - no )

Finally : it was +++ yes >>> --- no ... in this case must stop ,

Before that , my answer ( D )

..... Thanks .

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

These primary areas of the shutdown process are: • Personnel • Operational Capability/Requirement • Technology • Facilities/Hardware/Software/Program Security • Contracts • Budget

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

It is option C.

First thing to do before stopping a project is " completing & settling contracts including resolution of any open issues / items ". 

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟