ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

When analyzing risks using the certainty vs uncertainty spectrum,the term “unknownunknown is best described as _?

 

A. at the extreme end of the uncertainty spectrum. They will definitely affect you, although you have no control over them.

B. items or situations whose existence can not imazine (“ who knew ?”).

C. items that will effect you ,although you are not able to predict how or how much they will effect you?

D. rework.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/09/30
Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Most appropriate is B . If option B was not there option A would have been the right choice.

A. at the extreme end of the uncertainty spectrum. They will definitely affect you, although you have no control over them.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟