ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

In which of the following process is the qualified sellers list developed?

  

A. Plan Purchase And Acquisition

B. Request Sellers Responses

C. Plan Contracting

D. Select Sellers

 

 

 

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/08/26
Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation, Muhammad.

Answer obiviously is D - Select Sellers.

Select Sellers ( which is one of the output of the conduct procurement process ) is the process where sellers list is developed.

Taracius Dharmendra Joseph
من قبل Taracius Dharmendra Joseph , Business Development Manager & Supply Chain management , AVSCO Fzco - Subsidiary of Corner Stone Valves Co.,

The process of pre approved or prequalified list of prospective seller are developed for contractual services. When you have diffficulty in assessing the quality, standards and services the seller can provide. 

Reji George
من قبل Reji George , Business Development Consultant , Al Rais Group Of Companies

Generally it depends on the demand and organization types. We can't precisely conclude on your options. Generally 1) RFP

Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-A Plan Purchase And Acquisition

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟