ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The contract management plan is an output of which process?

 

A. Select sellers

B. Plan purchases and acquisitions

C. Plan contracting

D. Contract administration

E. Request sellers

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/08/06
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The best option given in show details is

A. Select sellers

appa anand badipetla
من قبل appa anand badipetla , Deputy Manager-Designs , PES ENGINEERS PVT Ltd

Plan Contracting  :  As per PMI its Procurement management plan

Nadjib RABAHI
من قبل Nadjib RABAHI , Freelancer , My own account

A: select sellers

C: plan contracting

D: contract administration 

Mihaela Kovacheva
من قبل Mihaela Kovacheva , Organizational Manager , Baumax Bulgaria Ltd /Part of Baumax AG/

The contract management plan is a part of the procurement lifecycle. Its purpose is to help the professionals manage contracts and it starts before the contract is signed.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟