In which of the following documents will you find specific procedures for contract closure?

A. Project plan

B. Contract file

C. Contract terms and conditions

D. Procurement audit documentation

E. Contract change control system

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/07/30
Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

C. Contract terms and conditions...........................

mohamad Bakri
من قبل mohamad Bakri , Technical Manager , Eiffel engineering

A. Project plan ; it should be here

nadir abdul khader
من قبل nadir abdul khader , Senior Quantity Surveyor , AASA Middle East Contracting Co. LLC

C. Contract Terms & Condtions

Rudra Prasad dhungana
من قبل Rudra Prasad dhungana , document controller , Larsen & Toubro Ltd. Construction

Its c .Contract terms & condition clearly describe about contract closure procedure.

Marry Joy Climacosa
من قبل Marry Joy Climacosa , Purchase Assisant , Sea Pioneer Maritime LLC

Letter C- Contract Terms & Conditions.

BERNARDO GARCIA
من قبل BERNARDO GARCIA , Construction Manager , Mannvits Construction

International Contracts usually discusses the  "procedures for contract closures" in lengthy clauses at the General Terms and Conditions (usually Part A; Technical Requirements being Part B and Financial Requirement as Part C). In the General Terms and Conditions it specifically defines the Client's step by step and procedural approach to closing a project whether at satisfactory completion or whether in dispute. It also fairly discusses the role of the contractor the requirements to comply with the specific provisions.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Obiviously, answer is C - Contract terms & conditions

Kedar Bhattarai
من قبل Kedar Bhattarai , Accountant General , Sultha suplayers

vouchar, bank balance certyfcy

Gulshan Aghayeva
من قبل Gulshan Aghayeva , Contracts Manager , Masdar Azerbaijan

Such a vague question. What do you mean by closure? Closing a contract usually encompass a well-decided procedure on how, for example, a seller in acquisition contracts will exit the deed. Such terms are usually founds its special terms of the contract on exit and closure. If the question is about termination of the contract - the terms should be found in the Terms and conditions

Sikhumbuzo Vilakazi
من قبل Sikhumbuzo Vilakazi , Director Security , Cape Peninsula University of Technology

procurement policy and national procurement framework which support national legislative governing the acquisition of goods and services

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟