Project cost management is primarily concerned with which of the following?

a. Cost of human resources

b. Basis of estimates

c. Assessing total cost of ownership

d. Establish the cost performance baseline

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/18
Faisal Alam
من قبل Faisal Alam , Deputy Manager - QS , M3M India Pvt. Ltd.

From the available options it seems A is the corect ans.

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option D

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A – It is the cost of the resources needed to complete project activities. Per the PMBOK® Guide5th

edition, p 167.

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

Option D,

................................