ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Who ultimately controls changes to scope on a project?

a. The project manager

b. Senior management

c. The change control board

d. The customer

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/13
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D – Of course it’s the customer. Ask yourself, who is cutting the check for you to do all that work and what

are they willing to pay for? The PM certainly doesn’t and the CCB doesn’t fund your project. Sr.

Management can be subsumed under the customer heading.

Ahmed Mohamed Ayesh Sarkhi
من قبل Ahmed Mohamed Ayesh Sarkhi , Shared Services Supervisor , Saudi Musheera Co. Ltd.

option " D "                                   .

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

 

thanks for invition ,,,,,,,,,, my choice is option C

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

I think project manager should control the changes and CCB will approve the changes if they agreed

dalal alharbi
من قبل dalal alharbi

I apologize for the answer I leave the answer to the experts specialists in this field that's not my area.

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

c. The change control board    is most likely  responsible for approving and/or rejecting changes.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟