ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

How to make & Claim the extension of time document in MSP & P6?

user-image
تم إضافة السؤال من قبل Venkatesan kumar , Planning Engineer , Yokogawa Electric corporation Pvt Ltd
تاريخ النشر: 2016/02/23

You need to update the time schedule , clarify the new critical path , and attach the reasons for the delay for each process on the critical path .

 

Mohammed  irfan
من قبل Mohammed irfan , Planning Engineer , Tristar Engineering & Construction

It depends upon the Analysis. If you are going for Time Impact Analysis, then you have to insertion or add activities indicating delays or changes into an updated schedule representing progress up to the point when a delay event occurred to determine the impact of those delay activities.

Pratik Khadatare
من قبل Pratik Khadatare , trainee engineer , Arun construction

To work with the extension of time in both MSP or P6 we need to arrange the floats. changing the project duration in a effective manner is the only way to get the optimistic & effective planning.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟