ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

How to make an E.O.T for a Baseline when you are on the middle of the project and you do not have a monthly update before?

user-image
تم إضافة السؤال من قبل Osama El Sherif , Planing Manager , Al-Rashid Trading and Contracting Co.
تاريخ النشر: 2016/02/23
Mamoun Salama
من قبل Mamoun Salama

if you have approved baseline schedule, use the impacted as planned schedule analysis method because you have not an interval update 

Tarig Hussein Eltayeb Hamid
من قبل Tarig Hussein Eltayeb Hamid , Resident Engineer , Tebodin Bilfiger middle east

in addition to the above mentioned, you can use the breakdown of affected activities (duration of activity) and apply it on days of delay. other way as cost wise as per BOQ

Omar Abdelmaksoud
من قبل Omar Abdelmaksoud , Senior Contract Administrator , Orascom Construction

I agree with Mr. Maamoun, the solution is to use impacted as planned technique, you won't need schedule update.

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟