What is the procedure for calculating the efficiency of the project?

user-image
تم إضافة السؤال من قبل مهرداد کتامی پور- مهرداد محمد جواد , Project Planner Manager , Omrab Engineering Co
تاريخ النشر: 2016/01/16
Adil Ibrahim
من قبل Adil Ibrahim , Learning & Development Manager , McCann Worldgroup (Global Advertising and PR firm)

An efficient project achieves the most productivity while using only the resources necessary (resources are things like funds, time, human capital, etc).

 

To do a quick efficiency test, look at (or create) your RACI charts. This will give you a list of who was responsible for which task (too many people shouldn't be responsible for the same task), who was accountable for which task (one person shouldn't be accountable for too many tasks), and so on and so forth.

 

You can then map out how many tasks were over-assigned, and how many people were over or under-utilized.

 

Hope that helps a little bit.

 

-Adil

ARUN BENADICK
من قبل ARUN BENADICK , Planning /Scheduling Engineer ( Ksa ) , Eastern Trading & Contracting Company

The only way for finding the efficiency is by calculation Cost Performance Index (CPI), Shedule Performance Index (SPI, Cost Variance, Shedule variance.      This Formulas are included all the costs (manpower, material, machinery)

مهرداد کتامی پور- مهرداد محمد جواد
من قبل مهرداد کتامی پور- مهرداد محمد جواد , Project Planner Manager , Omrab Engineering Co

thanks for true answer , but don't forget resources are very emportant for planning like manpower,equipment and machinery . and for Calculation of efficiency you need actual operation for all activitys in project.

 

mehrdad