ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

If new PM joined the project and decide to kick you out of project, after 50% of the project completed , what the advice for correct action?

user-image
تم إضافة السؤال من قبل Abdullatif Rabata , Deputy Project Director , THALES Security Solution & Services Co.
تاريخ النشر: 2015/08/20

First we need to know why this PM is going to be kicked out. This need to be done by holding a meeting between the PM and the project sponsor to discuss this issue and the consequences to be affected for the project.

Ali Althaib
من قبل Ali Althaib , Wireline Senior Field Engineer , Schlumberger

1. Ask why ?

2. Ask for certificate of completed half of it.

3.If it is not fair, you will get better place, because you are qualified.

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟