If the delivered raw materials is non-conformance and may result to delayed operation? What will be our steps to resolve this event?

user-image
تم إضافة السؤال من قبل CAMILO MIRABEL , Quality Controller , Artnature Philippines Inorporated
تاريخ النشر: 2015/04/16
Tony Diab
من قبل Tony Diab , مراقب صحي , بلدية بلاط وتوابعها -Blat Municipality

Dear camilo , It is always based in priorities and product final performance impact which means in case the raw materials are non conform however it can still perform and the non conformance is a minor issue accept the materials and claim it as "accepted under déviation " in case Its a major issue and the production is a Must get marketing involved where low performing materials may have a spécial customer or market ; in case no blessing reject all materials you got no support your safe on all sides