What difference between PERT and CPM?

user-image
تم إضافة السؤال من قبل محمد يونس , مهندس مشرف , الشركة العامة للكهرباء
تاريخ النشر: 2015/04/08
mohamed khaled Abdul Hamid abo mosaa
من قبل mohamed khaled Abdul Hamid abo mosaa , مدير علاقات عامه , مودرن فوم لصناعه الاسنفج

  • In CPM, cost optimization is given prime importance. The time for the completion of the project depends upon cost optimization. The cost is not directly proportioned to time. Thus, cost is the controlling factor.

Ali Mohamed Ahmed
من قبل Ali Mohamed Ahmed , site engineering , شركة مقاولات

1.The Program Evaluation and Review Technique (PERT) is a project management technique or tool which is suitable for projects that have unpredictable activities while the Critical Path Method (CPM) is a project management tool which is suitable for projects that have predictable activities.

2.CPM uses a single estimate for the time that a project can be completed while PERT uses three estimates for the time that it can be completed.

3.CPM is a deterministic project management tool while PERT is a probabilistic project management tool.

4.CPM allows project management planners to determine which aspect of the project to sacrifice when a trade-off is needed in order to complete the project while PERT does not.

 

Mohamed Abdulrahman
من قبل Mohamed Abdulrahman , Senior Planning & Contracting Engineer , United Building Co. (UBC)

In1957 the Critical Path Method (CPM) was developed as a network model for project management. CPM is a deterministic method that uses a fixed time estimate for each activity. While CPM is easy to understand and use, it does not consider the time variations that can have a great impact on the completion time of a complex project. The Program Evaluation and Review Technique (PERT) is a network model that allows for randomness in activity completion times. PERT was developed in the late1950's for the U.S. Navy's Polaris project having thousands of contractors. It has the potential to reduce both the time and cost required to complete a project.

MOHAMMAD ATIF IQBAL atif
من قبل MOHAMMAD ATIF IQBAL atif , SENIOR CIVIL ENGINEER , ITCC

PERT is event oriented tool while CPM is a activity oriented tool.but most important thing is both are using for scheduling not for planing. for planing there is very known tools WBS (work break down structure).