Change requests can occur due to:

<p><strong>A. An external event such as a change in government regulation. </strong></p> <p><strong>B. An error or omission in defining the scope of the product. </strong></p> <p><strong>C. An error or omission in defining the scope of the project. </strong></p> <p><strong>D. a and c </strong></p> <p><strong>E. all of the above</strong></p>

user-image
تم إضافة السؤال من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
تاريخ النشر: 2015/01/08
VENKITARAMAN KRISHNA MOORTHY VRINDAVAN
من قبل VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.

All the first mentioned: A, B & C

Answer option : E.

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Change requests are made to ensure that the planned outcome of the project is achieved, so answer E

Elke Woofter
من قبل Elke Woofter , Project Assistant , American Technical Associates

http://www.aiopass4sure.com/pmi-exams/pmi-002-exam-questions/a-change-requests-can-occur-due-to.html

E. all of the above

Divyesh Patel
من قبل Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

E. all of the above

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Yes, the correct answer is ...............

E. all of the above