1. Looking for critical plant zones to be well in place after outage.

2. Reinstate first those areas which are critical.

3. Recall best staff for emergency.

4. Personally help your staff.

5. Inquiry of incident and fixation of responsibility.

Mohammed AlMadani
من قبل Mohammed AlMadani , senior Operator , barrick mining LTD

he should be calm and try to start plant as fast as they can .

after that make investigation and improve the staff work by training  